Kim, Dong Kil
Work for Following Power Industry Firm in Korea (1979 ~ 2015)
-
KEPCO E&C (1983~2015)
-
AMTAI Engineering (1981~1983)
-
CHON Engineering (1980~1981)
PROFESSIONAL CAREER
-
Hanbit Nuclear Power Unit 1,2 (Pipe Support Design) (1983 ~ 1084)
-
Hanul Nuclear Power Unit 1,2 (Field Engineering for Piping) (1984~1988)
-
Gumi CHP (85.5MW x1) Piping Design (1988~1991)
-
Pyeongtaek CCPP (530MWx1) Piping Design and Vender Document review (1991~1993)
-
Ilsan CCPP (450MWx1) Piping Design and Vender Document review (1993~1996)
-
Hanrim Gas Turbine (30MW x 1) Piping Design and Vender Document review (1994~1995)
-
Boryeong 3,4 SOx Facility Piping Design and Vender Document review (1996)
-
Buk-Jeju CCPP (75MW x 2) Piping Design and Vender Document review (1996~2001)
-
Ilsan CCPP Unit 2 Heating System Piping Design and Vender Document review (1999~2000)
-
Pusan CCPP (450MW x 4) General Arrangement & Piping Design (1996~2005)
-
Incheon CCPP (450MW x 1) General Arrangement & Piping Design (2002~2006)
-
Daegu Jukgok Area CHP (Combined Heat and Power) General Arrangement & Piping Design (2005~2008)
-
Bugok CCPP General Arrangement & Piping Design (450MW x 1) (2006~2008)
-
Incheon CCPP Unit 2 General Arrangement & Piping Design (450MW x 1) (2006~2009)
-
Seo-Incheon CCPP General Arrangement & Piping Design (2005~2008)
-
POSCO CCPP 5,6 (500MW x 2) General Arrangement & Piping Design (2009~2010)
-
IGCC Pilot Plan (300MW) General Arrangement & Piping Design (2010~2011)
-
Sejong CCPP General Arrangement & Piping Design (2010~2015)
-
Pyeongtaek CCPP Phase 2 Feasibility Study including General Arrangement & Piping Design (2011)
-
Seoul CCPP 1,2 General Arrangement & Piping Design (2011~2014)
-
Taean Thermal Power Unit 9,10 General Arrangement & Piping Design (2013~2015)