Work for Following Power Industry Firm in Korea (1979 ~ 2015)

  • KEPCO E&C (1983~2015)

  • AMTAI Engineering (1981~1983)

  • CHON Engineering (1980~1981)

PROFESSIONAL CAREER

  • Hanbit Nuclear Power Unit 1,2 (Pipe Support Design) (1983 ~ 1084)

  • Hanul Nuclear Power Unit 1,2 (Field Engineering for Piping) (1984~1988)

  • Gumi CHP (85.5MW x1) Piping Design (1988~1991)

  • Pyeongtaek CCPP (530MWx1) Piping Design and Vender Document review (1991~1993)

  • Ilsan CCPP (450MWx1) Piping Design and Vender Document review (1993~1996)

  • Hanrim Gas Turbine (30MW x 1) Piping Design and Vender Document review (1994~1995)

  • Boryeong 3,4 SOx Facility Piping Design and Vender Document review (1996)

  • Buk-Jeju CCPP (75MW x 2) Piping Design and Vender Document review (1996~2001)

  • Ilsan CCPP Unit 2 Heating System Piping Design and Vender Document review (1999~2000)

  • Pusan CCPP (450MW x 4) General Arrangement & Piping Design (1996~2005)

  • Incheon CCPP (450MW x 1) General Arrangement & Piping Design (2002~2006)

  • Daegu Jukgok Area CHP (Combined Heat and Power) General Arrangement & Piping Design (2005~2008)

  • Bugok CCPP General Arrangement & Piping Design (450MW x 1) (2006~2008)

  • Incheon CCPP Unit 2 General Arrangement & Piping Design (450MW x 1) (2006~2009)

  • Seo-Incheon CCPP General Arrangement & Piping Design (2005~2008)

  • POSCO CCPP 5,6 (500MW x 2) General Arrangement & Piping Design (2009~2010)

  • IGCC Pilot Plan (300MW) General Arrangement & Piping Design (2010~2011)

  • Sejong CCPP General Arrangement & Piping Design (2010~2015)

  • Pyeongtaek CCPP Phase 2 Feasibility Study including General Arrangement & Piping Design (2011)

  • Seoul CCPP 1,2 General Arrangement & Piping Design (2011~2014)

  • Taean Thermal Power Unit 9,10 General Arrangement & Piping Design (2013~2015)